Project :
Fit Out Work at Social Welfare centre in Bairro da Ilha Verde District
Owner / Client :
Macau Social Welfare Bureau
Contractor :
Top Builders Group Ltd.
Value of work :
MOP15.3M
Construction Period :
2019.07 - 2020. 02
This Fit-out project covered an 800 square meters area which including M&E works. A Special 20 tons extensive UPS system had been installed serving as back up battery for the elderly emergency alarm system. Since the work had been carried out while the center opened to public, extra safety measures had been taken and fit-out work had been carried out with special arrangement.