The driving of approximately 1,850 piles started in late February 13 and was expected to be completed in Dec 13. However, due to early handovers of other areas of site and smooth progress of works, the project team has managed to achieve earlier completion of the works.

Top Builders Group would like to thank Wynn, Leighton and its subcontractors for the assistance and cooperation given during the works.

Top Builders would also like to thank their project team for their excellent performance throughout the project.