Project : Diversion of drainage network and associated site formation works of Taipa Waste Water Treatment Plant

Owner / Client : GDI (Infrastructure Development Office of Macau)

Contractor : Top Builders International Co. Ltd.  

Value of Work : MOP53M

Construction Period : 2020.06 – 2021-02

This project generally comprises of a new section of DN1420-DN1500mm sewage drainage pipe (out of which 375m is to be constructed under seabed, an update of a rainwater discharge network of approx. 330m of various diameter, construction of seawall and other asscoiated works